Technopark PhaseIII

Click here for TECHNOPARK PHASE-III LAND ALLOTMENT DETAILS

 

TECHNOPARK Phase III is located in 92 acres of land adjacent to the TECHNOPARK PHASE-I Campus The Government of India has granted Special Economic Status for 27.5 acres of land.  TECHNOPARK has already commenced construction of 10 lakhs sqft IT Building in this campus.

 

A 110/11 KV substation has already been commissioned in the campus. TECHNOPARK currently in the process of creating infrastructure including internal roads, power, water distribution systems and other amenities.

 

Master Plan

 

FACT SHEET

 

  • Project Area – 92 acres

 

  • 10 kms from Trivandrum City

 

  • 8 kms from Trivandrum International Airport

 

  • Type of Development : SEZ/ Non-SEZ

 

  • Basic Infrastructure – Power, Water. Roads, Telecom, Datacom, Sewage Treatment Plant, Utility Building, Food Court, etc

 

 

OFFERINGS

 

  • SEZ/ Non-SEZ land parcels available for IT/ITES Companies and/or developers on long lease

 

  • SEZ built-up area available on monthly rental basis to be ready by October 2011.

 

 

A. TECHNOPARK PHASE III (updated on 14.10.2011)

 

I.   WORKS IN PROGRESS


1). Construction of IT Building complex.

 

 


 

Present Status

 

 

Tower A

 

  • Ground floor column concreting work 100 % completed.

 

  • First Floor Column Concreting work 100 % completed.

 

  • Second Floor Column Concreting work 100 % completed.

 

  • Third Floor Column concreting work 100 % completed.

 

  • Fourth Floor Column concreting work 100 % completed.

 

  • Fifth Floor Column concreting work 100 % completed.

 

  • Sixth Floor Column Concreting work 100% completed.

 

  • Seventh floor column concreting work 100% completed.

 

  • Eight floor column concreting is in progress.  100% columns casted.

 

  • Ninth floor column concreting is in progress. 100% columns casted.

 

  • Tenth floor column concreting is in progress. 100% columns casted.

 

  • Glazing work in progress.

 

 

 

Tower B

 

  • Ground floor slab 100 % completed.

 

  • First floor slab 100% completed.

 

  • Second Floor Slab 93% completed.

 

  • Third Floor Slab casting 100 % completed.

 

  • Fourth Floor Slab casting 100 % completed.

 

  • Fifth Floor Slab casting 100 % completed.

 

  • Sixth Floor Slab casting 100% completed.

 

  • Seventh floor slab casting 100% completed.

 

  • Eight Floor  slab casting 100% completed

 

  • Ninth Floor Slab 100% completed.

 

  • Tenth floor slab 100% completed.
  • Eleventh floor 100% completed.

 

  • Glazing work in progress.

 

 

 

DG Building & Cooling Tower

 

  • All the structural work (pile, pile cap, columns & slabs) of DG Building completed.

 

  • All Piles and pile caps of cooling tower completed.

 

Major Milestones achieved:

  • Structure of 10 Lakh Square Feet  IT Building Completed

 

 




 

 

 

 

 

 

2) Site Development, Construction of roads etc:

 

 

Present Status


  • Earth filling work at site virtually completed.

 

  • Pipe Culvert work at canal diversion completion.

 

  • Pipe Culvert and Manhole work at Canal Diversion Completed.

 

  • Cable duct work through UST Phase II Campus completed.

 

 

 

3) Embankment protection work

 

Present Status

  • West side  total 625Rm in that 425Rm completed and balance 200 RM up to 3rd layer was completed.

 

  • Canal Diversion 160 RM ((4 Layer Side A) and (B side 4 Layer)) completed.

 

  • East side  total 820Rm in that Dry rubble 507 RM ,First Layer 507 RM ,Second Layer 507 RM & Third layer 507 RM is completed.

 

 

 

 



 

 

 

 

 

4) Electrification Of  IT Building


Present Status


  • Schematic SLD approval From KSEI obtained.
  • All the drawings are approved.
  • All the Technical submittals are approved.
  • Transformer and HT panel received and positioned.
  • DG erection and Acoustic work completed. DG Exhaust pipe foundation work in progress.
  • Cable Tray Route drawing approved.
  • Conduiting work in Tower A:- up to 6th floor 70% and from 7th to 10th floor 50%completed . Tower B: - upto 4th floor 70% and  from 5th to 8th floor 50% completed
  • Store room & Site office work completed.

 

Major Milestones achieved: KSEI Approval obtained for electrical scheme drawings.

 



 

5) HVAC  for IT building Complex


Present Status


  • 60% of the pipes received at site.
  • 70% of the Ducts are received at site
  • Duct erection started at 2nd, 3rd& 4th floor of Tower A.
  • Pipe erecting completed from 2nd to 8th floor lobby area of Tower A.
  • Butterfly valves, Y strainers, Flexible connectors received at site.

 

 

6) Water Distribution System

 

Present Status

  • Piling and Pile Cap Overhead tank A & B completed.

 

  • Piling and Pile Cap for Underground sump completed.

 

  • Shear Wall for Overhead Tank A and B in Progress

 

  • Pile cap of OHT A&B completed

 


Over Head Tank Works

 

7) Lifts for Phase III

Work awarded to M/s. Kone Elevator India Pvt. Ltd.

 

STATUS OF OTHER WORKS

 

1. Sewage Treatment Plant (STP)

Bid-1 Opened on 23/02/2011. Tender evaluation in progress

 

2. Fire Protection System for Phase III

Tender document prepared and will be floated soon.

 

3. Rain water harvesting

Tender document is under preparation

 

4. Internal Roads and Ducts

Tender document prepared and will be floated soon

 

5. SBC at IT Building Complex at Phase III

Tender document is under preparation

6. Landscaping Works for IT Building at  Phase III

Tender document is under preparation

 

6. 11kV Power Distribution System

Tender Evaluation under progress